| |
MUNICIPAL PROJECTS - Page 2
|
|
RAE Water & Sewer District 313
Wastewater Facility Upgrade
Bozeman, Montana
Allied Engineering was hired to
finish an incomplete Preliminary Engineering Report that
was abandoned by two previous consultants. The collection
system within the District was suffering from severe
leakage. An Infiltration and Inflow study was performed
to evaluate problem areas and to establish a punch list
of priority repair areas.
Allied completed the PER
for the wastewater system improvements and was retained
to complete the facility design. The $2.3 million upgrade
to the Sewer District’s leaking wastewater
lagoons is a state-of-the-art nutrient removal wastewater
treatment facility and a sequencing batch reactor (SBR).
This facility is the first of its kind to be constructed
in Montana and will be the basis for new MDEQ design regulations
for all future Sequencing Batch Reactors.
Allied provided complete civil engineering, structural
engineering, construction inspection and testing services.
Funding sources for the project include DNRC, CDBG, RUS,
and TSEP.
|
|

MDT
Article in
Construction
Today Magazine (Spring 2004)
with a bio of Allied Engineering
|
Montana Department of Transportation (MDT)
U.S. Highway 93, McClure Rd. to N. Arlee Couplet
Arlee, Montana
Allied Engineering provided
comprehensive design services for the reconstruction of a
6 mile segment of US-93 for MDT. This project was part of
the large-scale design effort, under the Design Management
team of Skillings-Connolly, to reconstruct 56 miles of US-93
from Evaro to Polson. The project was a unique partnership
between MDT, FHWA, and the Confederated Salish and Kootenai
Tribes and was considered a “landmark” project
for this area of the country.
This project included: rural and urban roadway reconstruction,
a new couplet around Arlee, reconstruction of twelve county
roads, and accommodating extensive irrigation systems that
cross or parallel the project. The downtown Arlee segment
involved extensive landscaping, curb & gutter, decorative
sidewalk, concrete intersections, decorative lighting, intersection ‘bulb-outs’ for
pedestrian safety, ADA ramps to existing buildings, and on-street
parking. There were also 1.5 miles of multi-use trail design
planned for south of Arlee. The Hydraulics group designed
a new storm drain system for Arlee, including retention and
detention ponds, and a 2,300 foot open channel outfall. AESI
also provided additional surveys, traffic warrant studies,
pavement design, signing & striping plans, erosion control
plans, geotechnical investigation, public involvement, and
final plan set production.
There were many unique and challenging design issues throughout
this complex corridor. These included sensitive environmental
and tribal cultural issues, architectural designs, and wildlife
considerations. Allied Engineering welcomed the extensive
design coordination and detailed effort a project of this
magnitude requires. This project gave us solid experience
with coordination efforts between MDT, Design Management
Team, Project Architects, Tribal Representatives, Flathead
Agency Irrigation District, MRL, Arlee Sewer District, Utility
Companies, and the residents of Arlee. The project was started
in April 2002 and the design was completed in August 2004.
The estimated construction cost was $15 million.
|
|
|
Montana Department of Transportation (MDT)
Boulder Main Street Reconstruction
Boulder, Montana
Allied Engineering designed
this 0.6 mile urban reconstruction project through Boulder,
Montana. This project involved extensive landscaping in medians,
accommodating large truck movements, decorative sidewalks,
on-street parking, water line adjustments, new storm drain
system, outfall and detention pond, and ADA ramps to existing
buildings. Allied also performed surveying, right-of-way,
geotechnical, hydrology and hydraulics, traffic studies & evaluation,
roadway design, signing & striping, and public involvement.
In
order to resolve parking and driveway issues, Allied worked
with a citizen’s group, business owners, schools,
and residents. During the project, Allied also worked closely
with the Town of Boulder to resolve other design issues.
The project design was started in 1999 and the construction
was completed in the summer of 2003. The construction cost
was approximately $3 million.
|
|

 
|
Montana Department of Transportation (MDT)
Boulder River Bridge Reconstruction
Boulder, Montana
Allied Engineering was the prime consultant for this bridge
replacement project, which connects to the Main Street Boulder
Project. Allied performed all the surveying, right of way,
geotechnical, hydrology and hydraulics, road design, traffic
counts and a traffic evaluation, signing design and layout,
and public involvement for the project.
Allied provided hydraulic
modeling of existing bridge and recommended bridge alternatives
using HEC-RAS River Analysis System software. Environmental
work was sub-contracted to Hyalite Environmental, LLC and
structural design was sub-contracted to Wells Engineers.
The new bridge is a two span pre-stressed concrete structure
about 54 meters in length. The design was completed in 2001.
|
| MUNICIPAL
PROJECTS - Page 1 |
Municipal | Commercial | Residential |
Water Resources | Clients |
|
|
|